CSPR 3-2021-9915 Watson Road- Major Site Plan

Summary: A Major Site Plan for McDonald's to tear down and rebuild a new fast-food restaurant.

Status: Public meetings have concluded, site plan was approved with conditions. Construction is anticipated to begin Spring 2022.

Process Table:

Application Submitted 3/16/2021
Comment Letter Sent3/30/2021
2nd Submittal Received4/8/2021
Board of Zoning Adjustment6/10/2021Variances approved for landscape buffer, structure setback, and fencing material
Planning and Zoning Commission6/2/2021Major Site Plan approved by P&Z Commission

Related Documents:

Board of Zoning Adjustment Public Hearing

Staff Report- 9915 Watson Rd. (McDonalds)- Major Site Plan Review